Analysis of Main Causes and Handling Measures for Flange Leakage

Date:2025-12-01View:1200Tags:SSAW Pipe,Steel Section,petro-chemical

Firstly, analyze the causes of flange leakage

For flange seals, leakage is related to various factors, including the physical properties of the sealing medium, operating conditions, roughness of the flange sealing surface, clamping force, quality of the flange itself, as well as the basic conditions, dimensions, and loading and unloading process of the gasket. In a certain device, the dissimilar steel welded joint on the outer flange of the outlet pipeline of DC102 hydrocracking reactor cracked and leaked under high temperature, high pressure, and hydrogen exposure conditions.
Due to the replacement of the metal ring gasket in the K201 pre hydrogenation reactor of the reforming unit after the last major overhaul, there has been no leakage during two and a half years of operation, and the sealed process medium and flange remain unchanged. Therefore, the influence of operating conditions can be considered separately.
01: Statistical analysis shows that during the period when leakage was detected in the last reactor inspection, approximately 20 start-up and shutdown cycles were experienced. Under specific pressure and temperature conditions, gaskets may experience fatigue failure, leading to leakage.
02: Long term high temperature can cause creep and stress relaxation of bolts and gaskets, thereby reducing the sealing pressure of gaskets. The bolt will be stretched and the flange will deform. If the residual sealing pressure is lower than the minimum working sealing pressure, leakage will occur.
03: Once a leak occurs, high-pressure material will overflow from the leak point, eroding the sealing surface and causing radial pitting.
Part 2: Leakage Prevention Measures, Flange Repair, and Assembly
1. Avoid abnormal temperature fluctuations and excessive heating and cooling rates during startup and shutdown.
Try to minimize unplanned shutdowns and avoid drastic temperature changes inside the reactor, thereby reducing temperature gradients.
01: During shutdown and material supply stoppage, flushing hydrogen should be slowly introduced into the fresh feed and circulating oil pipes to prevent leakage of high-temperature and high-pressure flanges due to rapid cooling. If the flange leaks due to cooling, steam should be used immediately to blow the oil and gas to prevent fire.
02: The thermal expansion and stress during the heating process of the equipment can cause minor leaks at the connection between the flange and gasket. When such a leak occurs, a steam hose should be placed at the leak point to blow away oil and gas and prevent a fire from occurring before tightening the connection. To minimize the harm of thermal expansion, the heating rate should generally not exceed 25 ℃/h.
03: After maintenance or during the first start-up, the bolts on the equipment pipeline may have been replaced or disassembled. These bolts are tightened at room temperature (cold state), while in normal production processes, bolts are tightened at higher temperatures.
2. Repair of flange sealing surface
Due to uneven corrosion on the contact surface of the flange ring, it must be repaired in accordance with the "Technical Supervision Regulations for Pressure Vessel Safety". The equipment connection flange is connected to the equipment body and can be repaired on site using specialized tools. These specialized tools consist of a support plate, a central axis, and a tool holder.
3. Selection of high-performance gaskets and digital technology
The selection of high-performance gaskets is crucial for reforming and hydrogenation reactors operating within a wide temperature range. Meanwhile, by combining high-precision constant torque tightening technology, digital on-site flange assembly quality assurance process control technology, and online monitoring and prevention technology for sealing status, the sealing performance and reliability of the flange can be further improved. In addition, selecting high-temperature resistant bolts is one of the key measures to ensure that the leakage rate is extremely low or minimized during the overhaul cycle after the inlet and outlet flanges of the hydrogenation reactor are insulated. This can effectively reduce energy consumption and environmental pollution, while improving production efficiency and safety.
4. Flange sealing assembly: Online continuous monitoring data and leakage trends of flange sealing status help enterprises timely understand the operating status of equipment and prevent potential safety hazards. Real time monitoring and analysis of flange sealing data can provide customers with scientific and reasonable suggestions on when to perform hot tightening, thereby reducing equipment failure risks and ensuring production safety.
3、 Running results after repair
After the flange repair, a new elliptical metal ring gasket was installed. After on-site polishing, pressure testing, and air tightness testing, it was put into operation. No leakage occurred during a major overhaul cycle. During regular maintenance, the flange sealing surface was disassembled and inspected, and it was found to be in good condition.